While the rain drops hurry up to experience the site of ‘Statue of Equality’, we merrily present to you the current state of the project!

  • 11 vehicles of finished products ready to be fixed as part of the statue
  • Sheet metal production of Flag pole is complete, Steel structure production is in progress
  • 3 vehicles of finished products ready to be fixed as part of the Dynamic Fountain
  • Fabricating of action mechanism is in progress
  • 10 copper plates of second level of body and 6 copper plates of foot fixed at site
  • Finished full welding of lotus petals of fifth level, sixth level welding of lotus petals is in progress
  • 230 beams are erected out of a total of 240 beams in the Bhadhravedi area
  • 7th consignment shipped on the 27th June, next shipment by 05th July!