While the rain drops hurry up to experience the site of ‘Statue of Equality’, we merrily present to you the current state of the project!
- 11 vehicles of finished products ready to be fixed as part of the statue
- Sheet metal production of Flag pole is complete, Steel structure production is in progress
- 3 vehicles of finished products ready to be fixed as part of the Dynamic Fountain
- Fabricating of action mechanism is in progress
- 10 copper plates of second level of body and 6 copper plates of foot fixed at site
- Finished full welding of lotus petals of fifth level, sixth level welding of lotus petals is in progress
- 230 beams are erected out of a total of 240 beams in the Bhadhravedi area
- 7th consignment shipped on the 27th June, next shipment by 05th July!
It is great to read this news, but it’s a whole new and elated experience to actually watch the progress and be part of it. So, we request all readers to come forward and Visit the Site.