While the rain drops hurry up to experience the site of ‘Statue of Equality’, we merrily present to you the current state of the project!

  • 11 vehicles of finished products ready to be fixed as part of the statue
  • Sheet metal production of Flag pole is complete, Steel structure production is in progress
  • 3 vehicles of finished products ready to be fixed as part of the Dynamic Fountain
  • Fabricating of action mechanism is in progress
  • 10 copper plates of second level of body and 6 copper plates of foot fixed at site
  • Finished full welding of lotus petals of fifth level, sixth level welding of lotus petals is in progress
  • 230 beams are erected out of a total of 240 beams in the Bhadhravedi area
  • 7th consignment shipped on the 27th June, next shipment by 05th July!

It is great to read this news, but it’s a whole new and elated experience to actually watch the progress and be part of it. So, we request all readers to come forward and Visit the Site.

For More Photos Click Here

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest Posts

Statje_of_Equality_logo_with_title_copy-removebg-preview

Jai Srimannarayana

Registration

Stay Connected with Statue of Equality & Teachings of Sri Ramanujacharya