9th Weekly Report of the Project from China
Report dated 29th,Aug,2016 The 1:1 model construction of Bhagavad Ramanujacharya is 90% complete. We will be finishing the 1:1 model manufacturing of statue before Sep,2016. Casting of Lotus and Elephants is complete. Body part casting is in progress....![8th Weekly Report Of the Project from China](https://statueofequality.org/wp-content/uploads/2016/08/8th-Weekly-Report-Of-the-Project-from-China.jpg)