5th Weekly Report of the Project from China
Report dated 25th,July,2016 1:1 model construction of Bhagavad Ramanujacharya is under progress. More than 50% of it is complete and casting of the deity has begun. Manufacturing of the other part of deity is 50% complete. 1:1 model manufacturing of the lotus is 75% complete. Casting of the lotus is in progress. 36 elephants and the ring behind them is completed […]
Statue Of Equality(Ramanuja Sahasrabdi) – Foundation Stone Laid
HH Sri Chinna Jeeyar Swamiji laid the foundation stone for 216 Feet “Statue of Equality – Samatha Murthi” in the sprawling new 45 acre area in JIVA Campus in Sri Ramanagar on the outskirts of Hyderabad on 2014 May 2nd Akshaya Thruthiya Day – One of the most auspicious days in a year, the day on which any good […]