8th Weekly Report Of the Project from China

8th Weekly Report Of the Project from China

Report dated 19th,Aug,2016 1:1 model construction of Bhagavad Ramanujacharya is 80% complete. Casting of the Deity has begun and is in progress. Body part casting is also in progress. Lotus and elephants casting is complete.   8th Week – Workshop...
6th Weekly Report of the Project from China

6th Weekly Report of the Project from China

Report dated 5th,Aug,2016 1:1 model construction of Bhagavad Ramanujacharya is under progress. More than 50% of it is complete and casting of the deity  has begun. Manufacturing of the other part of deity is 80% complete. 1:1 model manufacturing of the lotus is...