6th Weekly Report of the Project from China

6th Weekly Report of the Project from China

Report dated 5th,Aug,2016 1:1 model construction of Bhagavad Ramanujacharya is under progress. More than 50% of it is complete and casting of the deity  has begun. Manufacturing of the other part of deity is 80% complete. 1:1 model manufacturing of the lotus is...
5th Weekly Report of the Project from China

5th Weekly Report of the Project from China

Report dated 25th,July,2016 1:1 model construction of Bhagavad Ramanujacharya is under progress. More than 50% of it is complete and casting of the deity  has begun. Manufacturing of the other part of deity is 50% complete. 1:1 model manufacturing of the lotus is...